Which identities should the drawing distinguish?

Keep the rack PDU identity, physical outlet label, electrical bank or circuit, and any logical control group in separate fields. A drawing can use one identifier while a management interface uses another. Do not assume identical numbering means the two records describe the same boundary.

Schneider Electric's switched rPDU troubleshooting FAQ distinguishes bank circuit breakers from outlet enablement indications. That model-family example supports checking the selected equipment arrangement. It does not establish a universal bank layout or give permission to switch an outlet.

Critical Power Drafting is independent and is not affiliated with Schneider Electric. Use the actual current manual and approved project design. Engineering sign-off is performed only by the registered engineer on the job.

Sources: Schneider Electric: Switched rPDU bank breakers and outlet indications

Which fields belong in an outlet mapping worksheet?

Create one row per physical outlet in the scope of the drawing review. Preserve the manufacturer outlet labels exactly and retain the source revision. If the model evidence does not identify a bank, leave that mapping unresolved.

Rack PDU outlet and bank mapping
FieldSource to recordCheck
Rack and PDUProject equipment scheduleWhich physical PDU is being described?
Physical outletActual manufacturer outlet identifierNo inferred renumbering
Electrical bankSelected model bank diagramBank mapping is supported by that model
Protective deviceApproved bank protection referenceNo assumed rating from an adjacent bank
Incoming supplyControlled single-line and circuit scheduleUpstream reference resolves to this PDU
Logical control groupManagement configuration reference if relevantControl grouping stays separate from circuit identity
Connected load referenceApproved cable or equipment scheduleDocumentation covers the intended connection

How can two labels conceal a mismatch?

Illustrative example. A fictional PDU-DEMO labels a physical receptacle Outlet 05. Its approved model drawing places that outlet in Bank B, while a configuration export calls a control group Group 1. A draft cable schedule records Outlet 05, Bank 1 because the writer copied the control-group number. The mismatch is a drawing query; the group number does not establish the electrical bank.

Record the model drawing, configuration export and affected cable schedule revision together. Ask the drawing owner to confirm the mapping. Do not change the live configuration, operate a breaker or move a load to make the documentation appear consistent.

When a PDU model is substituted, reopen the mapping rather than keeping the previous bank relationships. An unchanged rack name or similar-looking enclosure does not establish identical internal grouping.

What should be checked before issuing the drawing pack?

Follow each physical outlet back to the approved model evidence, then follow each incoming PDU supply to the controlled circuit schedule. Record missing links and ambiguous labels at the correct equipment level. A complete list of outlet numbers can still have an unresolved bank or supply reference.

Keep A and B project supply labels tied to the approved design. Labels alone do not prove independence, capacity or redundancy. This worksheet documents identity and references; load assessment and electrical design remain separate technical work.

Retain a revision note explaining approved mapping changes. A later reviewer should be able to distinguish a corrected label from a changed equipment arrangement. No installation, switching or energization is authorised by this drawing guide.

Common questions

What else should the bid team know?

Is an outlet control group the same as a protective bank?

Do not assume that. Check the selected model and retain separate identifiers.

Can the previous mapping be kept after a model substitution?

Only where the actual new equipment evidence and approved review support it.

Does an outlet map prove spare electrical capacity?

No. Capacity and design checks require their own authorised assessment.

Primary sources

  1. Switched rPDU bank breakers and outlet indicationsSchneider Electric