Why is a runtime note more than a number of minutes?

Eaton provides separate runtime resources for selected UPS models and configurations with or without optional battery packs. This supports tracing a runtime figure to the actual product and battery arrangement. It does not establish a runtime for an unspecified data center installation.

Critical Power Drafting is independent and is not affiliated with Eaton. The design owner approves the required load case and runtime evidence. A drafter coordinates those approved inputs across the drawings and schedules.

Sources: Eaton: Eaton UPS battery runtimes

Which evidence belongs beside the drawing note?

Separate the required duration from the supported duration reported by a selected source. A schedule that copies a requirement into a performance field conceals whether the arrangement was actually assessed.

Which evidence belongs beside the drawing note?
FieldRecordCheck
RequirementRequired duration and load caseIdentify the approved design basis
EquipmentUPS model and configurationMatch the exact selected resource
LoadValue, unit and operating caseKeep kW and kVA definitions clear
BatteryApproved arrangement and condition basisDo not infer from cabinet count
Runtime evidenceCurve or calculation revision and conditionsRecord the actual applicable point
ApprovalEngineering disposition and drawing revisionLeave unsupported figures open

What does a load mismatch look like?

Illustrative example. A fictional schedule requires 10 minutes at 80 kW. Its supporting note merely says 15 minutes at 40 kW for a named assumed arrangement. The 15-minute figure does not prove the 80 kW requirement is met. The missing 80 kW evidence stays open for the design owner.

Do not halve the duration, double the battery count or interpolate a curve without the manufacturer and engineer-approved basis. The invented figures are not product performance, a battery sizing method or evidence that the installed system passes or fails.

How should a changed battery arrangement be handled?

Link the approved change to the runtime evidence as well as the battery schedule and one-line reference. Keep the earlier assessment with its original configuration. A correct count reconciliation can coexist with an outdated performance reference.

Do not commission batteries, alter connections or authorize a load test from this worksheet. Engineering sign-off is performed only by the registered engineer on the job.

Common questions

What else should the bid team know?

Does a UPS kW rating establish runtime?

No. Runtime needs the actual load and battery arrangement evidence.

Does twice the cabinet count guarantee twice the runtime?

No. Use the approved manufacturer and engineering assessment.

Can a requirement be copied into the supported-runtime field?

Only actual supporting evidence establishes that field; keep the requirement separate.

Primary sources

  1. Eaton UPS battery runtimesEaton